Idalia Culvert Crossing @ Arroyo de la Barranca

Project Manager: Arnell Friedt
Office Phone: (505) 896-8242
E-Mail: afriedt@rrnm.gov
Contract Company: Weston Solutions
Cost: $ 191,361.76
Stage: Final Design
Schedule: September 2021 - February 2023
IMG_0147

This project includes the design, right of way acquisition, and construction of the Idalia Road Culvert Crossing at the Arroyo de la Barranca. The existing culvert pipes and headwall will be removed and replaced with a box culvert.

Funding for this project is from City funds (approximately $201,000) and federal funds (approximately $1,179,000).

Public Meeting

A virtual, public meeting was held on  May 25, 2022 from 5:30pm - 6:30pm. To view the presentation slides, click or tap here.


Status Log:

  • November 2022: Working toward 90% Design and completing Right of Way maps.
  • August 2022: Right of Way maps in development. 
  • July 2022: Begin 90% Design.
  • June 2022: 60% Design complete.
  • April 2022: Working towards 60% Design.