This project includes the construction of an asphalt pedestrian path along the north side of Westside Blvd from Unser Blvd to City Limits. Work will include asphalt paving, ADA compliant curb ramps, intersection lighting, re-use water line extension, and landscaping.
Total funding for this project is from City funds (approximately $223,029.00) and federal funds (approximately $1,125,463.00).
Outside lane closures will occur on westbound Westside Boulevard during working hours (7 a.m. to 5 p.m.) starting May 9, 2022.
The intersection of Trailside Road and Westside Boulevard will be closed from June 1 to approximately mid-June. When this intersection reopens, the intersection of Caramesa Drive and Westside Boulevard will be closed for approximately 10-14 days.
Status Log:
April 2022: Preparing for start of construction
March 2022: Working on pre-construction approvals and submittals